VARIATION CLAIM FOR THE COMPLETION OF UNDER CONSTRUCTION OF NEW WATER SUPPLY SCHEMES AT MAMMA, TAMBUWAL, OLD AIRPORT AND RUGALIWAN FOR SOKOTO METROPOLIS AND ENVIRONS IN SOKOTO STATE
Procuring Entity: Ministry of Water Resources
Date of Award: 05 Jun 2024
Contract Award Information
| Project Name |
VARIATION CLAIM FOR THE COMPLETION OF UNDER CONSTRUCTION OF NEW WATER SUPPLY SCHEMES AT MAMMA, TAMBUWAL, OLD AIRPORT AND RUGALIWAN FOR SOKOTO METROPOLIS AND ENVIRONS IN SOKOTO STATE |
| Procuring Entity |
Ministry of Water Resources |
| Contractor’s Name |
M/S. CHINA ZHONGHAO (NIG.) LIMITED |
| Project Price |
₦14,138,289,057.55 |
| Date of Award |
05 Jun 2024 |
| Contract Duration |
— |
| Contractors Phone |
— |
| Contractors Email |
— |
| Tender Method |
— |
| Contract Scope |
— |